# 90-Day Command Companion (Field Page)
## LR • NWA • Texarkana • Plant Operations

**Use:** Daily field execution control sheet  
**Rule:** No open-end tasks (owner + due date + acceptance criteria required)

---

## A) Owner Command Checklist

### Zac
- [ ] Waterline path finalized (NWA → ADOH/BOB)
- [ ] Waterline contract + completion date locked
- [ ] Permits/plant/Tex progress updated
- [ ] Gerardo coordination check completed

### Tracy
- [ ] 90-day plan governance check complete
- [ ] Nathan follow-up closed
- [ ] Ian follow-up closed
- [ ] Accountability/escalation board current

### Dylan
- [ ] NOI Excel-in-bot workflow running
- [ ] HUD reporting updated
- [ ] Leasing reporting updated

### Jeremy
- [ ] Phase 3/4 large-scale status updated
- [ ] Materials ordering aligned to schedule
- [ ] Waste/shortage control check complete

### Stephan
- [ ] R Plan completion status updated
- [ ] Plant plan release package status updated

### Russ
- [ ] Refi capital action status updated
- [ ] Plant/Tex operations decisions logged
- [ ] Tech/software formation status updated

---

## B) Daily R/Y/G Command Board

| Priority Item | Owner | Due Date | Status (R/Y/G) | Blocker | Escalated? |
|---|---|---|---|---|---|
| Waterline contract/timeline | | | | | |
| Permits + utility approvals | | | | | |
| R Plan final release | | | | | |
| P3/P4 material flow | | | | | |
| NOI/HUD reporting integrity | | | | | |
| Tex trigger decisions | | | | | |

---

## C) 6:15 PM Executive Digest Input (Required)

1. Completed today:
- __________________________________________

2. KPI movement:
- NOI: __________
- Schedule: __________
- Permits: __________
- Materials: __________

3. Top blockers requiring executive decision:
- __________________________________________

4. Next-day top 3 priorities:
1) ________________________________________
2) ________________________________________
3) ________________________________________

---

## D) Escalation Standard
- Any task without owner/due date by EOD = RED
- Any slip >48 hours = mandatory escalation
- Verbal approvals on critical path items are not accepted; written confirmation required

---

## Signoff (Daily)
- Field Lead: _____________________ Date: ________
- Program Lead: ___________________ Date: ________
- Executive (Russ): _______________ Date: ________